November 5, 2026
What can you do with a brand-new 42.5-acre park when its portable restrooms are taken away the day after the ribbon-cutting?
The Woodridge Park District set the grand opening of Jubilee Point Park, 7101 Woodridge Drive, the site everyone in Woodridge called Town Centre for years, for Saturday, October 31, 2026, from 10 a.m. to noon. The District's own park page says portable restrooms are provided from April 1 to November 1, and the park has no permanent restrooms. As a result, the newest park in the village enters its first season with almost all of its new features waiting on spring. For the next few months, the parts worth using are the sled hill, which opened back in 2022, and a set of paved paths that run to the front door of Village Hall.
The calendar was supposed to work out differently. Downers Grove Wire reported that Schwartz Construction was scheduled to start in February 2025, but a long local permitting review pushed the start to June, and a wetter-than-normal summer in 2026 slowed the work further. Even in late August the Park District was still aiming for a September opening, with path paving, parking-lot striping, turf restoration and overhead utility burial left to finish.
The finished amenities are clearly built for warm weather. About 15 of the 42.5 acres were developed in this phase. They include a playground for ages 5 to 12 with poured-in-place rubber surfacing, two pickleball courts, a multi-sport court for basketball, futsal and deck hockey, Baggo courts, ping-pong tables, a community garden, and a picnic pavilion. The Park District calls the pavilion its largest shelter, built for 200 people and 18 picnic tables. The Park District has said the annual Woodridge Jubilee summer festival will continue to be held there, and some Summer Concert and Movies Under the Moon dates may move there too.
State grants paid for part of the project. The Park District lists a $600,000 Illinois Department of Natural Resources OSLAD grant and a $225,000 grant from the Illinois Department of Commerce and Economic Opportunity. The Phase 2 development cost is estimated at $2.8 million. In the District's grand opening announcement, Executive Director Jenny Knitter called it "a place where people can come together, try something new, stay active, spend time with family and friends and create memories for years to come."
All of that is built for months that are still ahead. Here is what the park offers between now and then.
The Park District's rules sort the new amenities by season fairly clearly.
| Feature | Winter status per Park District rules |
|---|---|
| Park hours | Dawn to dusk, every day of the year |
| Pickleball courts | Locked after the first sign of ice or snow; no lights |
| Multi-sport court | No lights; first come, first served |
| Paved paths, 2+ miles | 10 feet wide in most areas, ADA accessible, open to bikes and e-bikes |
| Restrooms | Portable units end November 1; no permanent restrooms |
| Challenge Course | Scheduled to open in late November 2026 |
| Sled hill | Open when conditions allow; status posted on the Rainout Line |
The Ninja Warrior-style Challenge Course is the only new feature scheduled to open during the cold months. It sits next to Jefferson Jr. High, is designed for ages 13 and up, and includes a 40-yard dash race element. "Dawn to dusk" also covers very little time in late November, and none of the courts have lights.
That leaves the oldest feature in the park as the main reason to visit this winter.
Before the playground or pavilion existed, the sled hill was Phase 1. The Park District says it opened for play on January 1, 2022, and the soil, grading and restoration came through a donation agreement at no cost to the District. It is now part of a larger park with 80 parking spaces: 62 in the main lot and 18 in the garden plots lot.
The sled hill rules posted on the Park District's Jubilee Point Park page are specific.
Before loading the car on a snow day, check the Woodridge Park District Rainout Line, which the District uses for sled hill status and park closures. Remember the restroom schedule too. After November 1, the nearest restroom is not in the park.
The 2026 construction may matter most this winter because of where it leads. The park's paved loops connect to the Woodridge Municipal Complex, Jefferson Jr. High and the neighborhood to the south at Sprucewood Avenue. At 71st Street and Woodridge Drive, they join the village-wide trail network toward Lake Harriet and Hawthorne Hill Woods. The Park District also says the parking lots south of Village Hall connect to the park's path system.
That connection matters on Saturday, November 21. The 2026 Woodridge Winterfest runs from 3 to 6 p.m. at Kagann Plaza at Woodridge Village Hall, 5 Plaza Drive. It is free and co-hosted by the Village, the Park District, the Woodridge Public Library, the Woodridge Special Events Committee and the Woodridge Volunteer Corps. The Village's schedule includes:
The event runs one hour shorter than last year. The Park District's 2025 listing ran from 3 to 7 p.m. The tree lighting at 5 p.m. comes close to sunset, so arriving by trolley from Cypress Cove or parking south of Village Hall puts you nearest the plaza.
The Woodridge Human Relations Advisory Committee is running the Winterfest Food Drive from November 16 through November 28. Nonperishable donations can be dropped off at Village Hall, 5 Plaza Drive, the Woodridge Public Library, 3 Plaza Drive, or the Park District ARC. At Winterfest itself, a donation table will be set up near the heated food tent.
Most of the park's value arrives with warm weather, but the first steps toward using it in 2027 happen in midwinter, and both have changed from how things worked before.
The community garden now has 65 spaces: 57 standard 20-by-30-foot plots, 6 raised-bed planters, and 2 spaces for managing organic garden waste. For 2027, each household can rent only one plot, previous renters get no priority, and reservations are first come, first served. The reservation dates are:
The 200-person pavilion follows a similar pattern. Reservations are taken in person only, at the ARC or FHCC front desks, starting January 18 for residents and February 1 for nonresidents. It is the only part of the park that can be reserved. The Park District says fees for both the garden plots and the pavilion will be recommended in its Annual Fees and Charges Ordinance in December, with separate resident and nonresident rates. If you want a 2027 garden plot or a summer party date at the pavilion, plan around that December fee schedule and the January 18 desk opening.
At the Wardlow Group, we keep track of what Woodridge adds, from Jubilee Point Park to the next project on the village's list, because those details shape daily life on the streets we work on. If you'd like to know how a new amenity like this one affects the value of your home, ask us for a free home valuation or a look at our off-market listings.
Stay up to date on the latest real estate trends.
DuPage County Tax Assessment: How It Works
Did You Know? District 99 Serves More Than Just Downers Grove!
Did You Know? New Construction Communities Are Also Available Within Downers Grove District 99!
Selling in Downers Grove? 7 Questions to Ask Before Hiring a Realtor
How to Choose the Best Realtor in Downers Grove, IL
Beyond Luxury and New Construction: Why Experience Selling Every Type of Home Matters
Etiam non quam lacus suspendisse faucibus interdum. Orci ac auctor augue mauris augue neque. Bibendum at varius vel pharetra. Viverra orci sagittis eu volutpat.